Name of State / UT WEST BENGAL  
 
I)? Slipped back habitations  
A) Physical Target (in numbers)  
Number of habitaions as on 1/04/2005   Not Covered (NC) 339   Partially Covered (PC) 10208
Yearwise Plan for Coverage  
Sl No. Programme   2005-06     2006-07     2007-08     2008-09     Total  
NC PC Total NC PC Total NC PC Total NC PC Total NC PC Total
1 ARWSP 153 1052 1204.65 - 1175 1175 - 1179 1179 - 1196 1196 153 4602 4755
2 Swajaldhara 34 234 268 - 261 261 - 262 262 - 264 264 34 1021 1055
3 State Sector 152 1051 1203 - 1170 1170 - 1183 1183 - 1181 1181 152 4585 4737
4 Other Sources * - - - - - - - - - - - - - - -
  Total 339 2337 2676 - 2606 2606 - 2624 2624 - 2641 2641 339 10208 10547
* Other sources would include projects undertaken with loans from External Institutions / Donors etc.
B) Funds requirement programme wise (Rs. in Lakh)
Sl No. Programme   2005-06     2006-07     2007-08     2008-09     Total  
NC PC Total NC PC Total NC PC Total NC PC Total NC PC Total
1 ARWSP 1126.00 7510.00 8636.00 - 8361.00 8361.00 - 8439.00 8439.00 - 8543.00 8543.00 1126.00 32853.00 33979.00
2 Swajaldhara 250.30 1668.00 1918.00 - 1858.00 1858.00 - 1875.40 1875.40 - 1899.00 1899.00 250.30 7300.00 7550.00
3 State Sector 1127.00 7509.60 8637.00 - 8362.00 8362.00 - 8440.00 8440.00 - 8543.00 8543.00 1127.00 32854.60 33982.00
4 Other Sources - - - - - - - - - - - - - - -
  Total 2503.00 16688.00 19191.00 - 18581.00 18581.00 - 18754.00 18754.00 - 18985.00 18985.00 2503.00 73008.00 75511.00
C
Fund Requirement (scheme wise) for each of the four years (2005-06)
S No. Type of Scheme No. of Habitations to be covered? Unit cost of Coverage (per habitation) (Rs. Lakh) Estimated Cost (Rs. Lakh)
NC PC Total NC PC Total NC PC Total
1 Spot Source 124 982 1106 3.27 2.45   405.00 2406.00 2811.00
2 PWSS                  
  (a) Groundwater   970 970   10.25     9943.00 9943.00
  (b) Surface Water                  
3 RWHS (Pond/ Roof Top) 115 153 268 1.43 1.07   164.00 164.00 328.00
4 Traditional Surces(PWSS based on Lake/ Spring) 100 97 197 19.34 14.50   1934.00 1407.00 3341.00
5 Others (PWSS based on Impoundment of Surface/ Sub-Surface Water)   135 135   20.50     2768.00 2768.00
  Total 339 2337 2676       2503.00 16688.00 19191.00
C
Fund Requirement (scheme wise) for each of the four years (2006-07)
S No. Type of Scheme No. of Habitations to be covered? Unit cost of Coverage (per habitation) (Rs. Lakh) Estimated Cost (Rs. Lakh)
NC PC Total NC PC Total NC PC Total
1 Spot Source   1090 1090 3.27 2.45     2671.00 2671.00
2 PWSS                  
  (a) Groundwater   1078 1078   10.25     11050.00 11050.00
  (b) Surface Water                  
3 RWHS (Pond/ Roof Top)   178 178 1.43 1.07     190.00 190.00
4 Traditional Surces(PWSS based on Lake/ Spring)   110 110 19.34 14.50     1595.00 1595.00
5 Others (PWSS based on Impoundment of Surface/ Sub-Surface Water)   150 150   20.50     3075.00 3075.00
  Total   2606 2606           18581.00
C
Fund Requirement (scheme wise) for each of the four years (2007-08)
S No. Type of Scheme No. of Habitations to be covered? Unit cost of Coverage (per habitation) (Rs. Lakh) Estimated Cost (Rs. Lakh)
NC PC Total NC PC Total NC PC Total
1 Spot Source   1098 1098 3.27 2.45     2690.00 2690.00
2 PWSS